HCC completes 3.82 km tunnel for Mumbai Metro III

by IANS |

Mumbai, Aug 2 (IANS) The Hindustan Construction Company (HCC) on Friday said that as part of the upcoming Mumbai Metro III project it had completed boring the first 3.82 km long tunnel passing underneath some of the most thickly populated areas of south Mumbai.

Terming it "a challenging task", a company spokesperson said HCC has finished the south-bound tunnel between Chhatrapati Shivaji Maharaj Terminus (CSMT) and Mumbai Central stations, becoming the first contractor among all others to complete the entire length of a tunnel for the Metro III project.

The HCC maintained an average drilling rate of around 8.20 metres per day for the 3.82 km long tunnel passing via the station boxes of Kalbadevi, Girgaon and Grant Road.

This section is part of the 33.50 km long Metro III line connecting Colaba-Bandra-SEEPZ (Andheri East) and will be the first fully underground metro in the city. It is being built at a cost of around Rs 23,136 crore, with a Rs 13,325 crore loan from the Japan International Cooperation Agency (JICA).

The HCC teams encountered several geological and urban challenges, including proximity to the Arabian Sea, tunneling through heterogeneous reclaimed land, congested working areas and drilling below some of the oldest residential and other buildings, many over a century old, without disturbing their foundations.

The Mumbai Metro Rail Corporation Ltd (MMRCL) had awarded the contract to HCC in July 2016 for the design and construction of twin tunnels by Tunnel Boring Machines (TBM) and construction of four underground metro stations at CSMT, Kalbadevi, Girgaon and Grant Road.

For the work, HCC procured two TBMs from China with 117 metre long single-shield dual-mode hard rock with a 6.68 metre diameter and weighing 848 tonnes, the company said.

These TBMs are equipped to operate in both - open or closed - modes, in the predominantly fresh, and slightly to moderately weathered Basalt and Breccia that was anticipated in the Mumbai Metro projects.

After months of geotechnical investigations, planning and procurement processes, the first TBM, Vaitarna I, was launched at CSMT on December 4, 2017. Its initial drive was completed on January 11, 2018, while the main drive ended in mid-February 2018 with a team of 32 people working on it, the spokesperson said. 

Since congested residential areas are located above the tunnel, structural surveys using sophisticated instruments were carried out prior to starting the boring work in a 30 metre influence zone on either side of the alignment to assess its impact on the buildings.

With the tunneling work completed well within the stipulated time, the HCC has now taken up the work of constructing the underground metro stations, each with a unique design.

Latest News
Israel mobilising two extra reserve units ahead of possible Rafah fight Wed, Apr 24, 2024, 04:45 PM
Two killed, 20 injured as tractor-trolley overturns in UP Wed, Apr 24, 2024, 04:44 PM
BJP MP's wife to contest against him from UP's Etawah Wed, Apr 24, 2024, 04:26 PM
91 pc of Indian firms will use half or more data to train AI models in 2024: Report Wed, Apr 24, 2024, 04:19 PM
PDP's Waheed Parra files nomination for Srinagar LS seat Wed, Apr 24, 2024, 04:03 PM
PCB to explore options if Team India doesn't play Champion Trophy in Pakistan Wed, Apr 24, 2024, 04:02 PM
Iran, Sri Lanka inaugurate Uma Oya multipurpose development project Wed, Apr 24, 2024, 03:48 PM
Karnataka to have 1.40 lakh polling officials in 14 LS seats Wed, Apr 24, 2024, 03:38 PM
AIFF technical committee recommends Chaoba Devi as coach of senior women's team Wed, Apr 24, 2024, 03:31 PM
Russian President's key aide visits Kabul, holds talks with Taliban leadership Wed, Apr 24, 2024, 03:13 PM
Repolling underway in eight polling stations in Arunachal amid heavy security Wed, Apr 24, 2024, 02:24 PM
Amid tension in Middle East, Iranian President arrives in Sri Lanka Wed, Apr 24, 2024, 02:00 PM
Delhi Minister Saurabh Bharadwaj meets CM Kejriwal in Tihar Wed, Apr 24, 2024, 01:49 PM
Campaigning on eight LS seats for second phase in UP ends today Wed, Apr 24, 2024, 01:30 PM
mRNA vaccine tech can be harnessed to prevent deadly diseases: Report Wed, Apr 24, 2024, 01:01 PM